Project Timetable

Task

Completion Date

Preliminary Engineering

8/3/2011

Environmental Clearance

4/16/2012

Geotechnical Investigations/Draft Foundation Report

11/18/2011

35% Plans and Estimate Submittal to County, Bridge Type Selection Report

3/14/2012

Traffic Handling Design (Detour)

3/14/2012

35% Plans and Estimate Submittal to Caltrans, Bridge Type Selection Report

3/30/2012

Utility Coordination/Design

3/1/2014

 

 

 

Right of Way

6/2014

Bridge Design & Detailing

11/16/2012

65% Plan, Specifications and Estimate

11/16/2012

 

 

 

Independent Bridge Check

7/1/2013

95% Plans, Specifications & Estimate

9/13/2013

Permitting

3/1/2014

 

 

 

Final PS&E Package

10/16/2014

Prepare Construction Authorization Request

10/16//2014

Caltrans Approval & Issuance of E-76

 

1/20/2015

County Advertise & Award

 

April 2015

Contractor Mobilization

 

May 2015

Construction Complete

 

Nov 2015