Project segment 3

The third segment, also on Big Creek Road, starts approximately 7.7 miles east of the Big Creek Road/Bucks Lake Road intersection at Buck's Lake and proceeds 1.1 miles east and north. This segment includes pavement rehabilitation, a mechanically stabilized retaining wall, and some drainage improvements.

mse work in progress

Construction of mechanical stabilized retaining wall is progressing and nearing completion

retaining wall

The mechanical stabilized wall consists of two foot lifts of welded wire face retaining reinforcement.

side view

The retaining wall has been completed. Project completion will come next year with repaving this area as well as paving some other areas on Big Creek Road.

below wall

An image of the wall taken looking up from Big Creek.